+#!/usr/bin/perl
+
+=head2 DESCRIPTION
+
+Tests the prorate_defer_bill behavior when a package is started on the cutoff day,
+and when it's started later in the month.
+
+Correct: The package started on the cutoff day should be charged a setup fee and a
+full period. The package started later in the month should be charged a setup fee,
+a full period, and the partial period.
+
+=cut
+
+use strict;
+use Test::More tests => 11;
+use FS::Test;
+use Date::Parse 'str2time';
+use Date::Format 'time2str';
+use Test::MockTime qw(set_fixed_time);
+use FS::cust_main;
+use FS::cust_pkg;
+use FS::Conf;
+my $FS= FS::Test->new;
+
+my $error;
+
+my $old_part_pkg = $FS->qsearchs('part_pkg', { pkgpart => 2 });
+my $part_pkg = $old_part_pkg->clone;
+BAIL_OUT("existing pkgpart 2 is not a prorated monthly package")
+ unless $part_pkg->freq eq '1' and $part_pkg->plan eq 'prorate';
+$error = $part_pkg->insert(
+ options => { $old_part_pkg->options,
+ 'prorate_defer_bill' => 1,
+ 'cutoff_day' => 1,
+ 'setup_fee' => 100,
+ 'recur_fee' => 30,
+ }
+);
+BAIL_OUT("can't configure package: $error") if $error;
+
+my $cust = $FS->new_customer('Prorate defer');
+$error = $cust->insert;
+BAIL_OUT("can't create test customer: $error") if $error;
+
+my @pkgs;
+foreach my $start_day (1, 11) {
+ diag("prorate package starting on day $start_day");
+ # Create and bill the first package.
+ my $date = str2time("2016-04-$start_day");
+ set_fixed_time($date);
+ my $pkg = FS::cust_pkg->new({ pkgpart => $part_pkg->pkgpart });
+ $error = $cust->order_pkg({ 'cust_pkg' => $pkg });
+ BAIL_OUT("can't order package: $error") if $error;
+
+ # bill the customer on the order date
+ $error = $cust->bill_and_collect;
+ $pkg = $pkg->replace_old;
+ push @pkgs, $pkg;
+ my ($cust_bill_pkg) = $pkg->cust_bill_pkg;
+ if ( $start_day == 1 ) {
+ # then it should bill immediately
+ ok($cust_bill_pkg, "package was billed") or next;
+ ok($cust_bill_pkg->setup == 100, "setup fee was charged");
+ ok($cust_bill_pkg->recur == 30, "one month was charged");
+ } elsif ( $start_day == 11 ) {
+ # then not
+ ok(!$cust_bill_pkg, "package billing was deferred");
+ ok($pkg->setup == $date, "package setup date was set");
+ }
+}
+diag("first of month billing...");
+my $date = str2time('2016-05-01');
+set_fixed_time($date);
+my @bill;
+$error = $cust->bill_and_collect(return_bill => \@bill);
+# examine the invoice...
+my $cust_bill = $bill[0] or BAIL_OUT("neither package was billed");
+for my $pkg ($pkgs[0]) {
+ diag("package started day 1:");
+ my ($cust_bill_pkg) = grep {$_->pkgnum == $pkg->pkgnum} $cust_bill->cust_bill_pkg;
+ ok($cust_bill_pkg, "was billed") or next;
+ ok($cust_bill_pkg->setup == 0, "no setup fee was charged");
+ ok($cust_bill_pkg->recur == 30, "one month was charged");
+}
+for my $pkg ($pkgs[1]) {
+ diag("package started day 11:");
+ my ($cust_bill_pkg) = grep {$_->pkgnum == $pkg->pkgnum} $cust_bill->cust_bill_pkg;
+ ok($cust_bill_pkg, "was billed") or next;
+ ok($cust_bill_pkg->setup == 100, "setup fee was charged");
+ ok($cust_bill_pkg->recur == 50, "twenty days + one month was charged");
+}
+